Paving on Trout Gulch Rd will continue on June 11 and will likely be completed on June 12. Please note, we will return to this area later in the project with two layers of seal.
Clearing the road edges of dirt and debris will begin on Soquel San Jose Rd starting Thursday, June 11. This will likely take several days to complete.
Edge clearing and digouts will begin on W Beach Rd and Lee Ave soon. We are coordinating with Watsonville City Water as they are currently completing a water main replacement on Lee Ave.
An updated 3-week look-ahead schedule will be posted soon.
CLICK HERE FOR PROJECT ROAD LIST (including treatments and limits)
Includes:
Soquel San Jose Road (Soquel Dr to Olive Springs Rd), Daubenbiss Avenue, Dawn Lane, and Shauna Court.
Please note that construction on these roads will be done as night work. We apologize in advance for any inconvenience this may cause to residents.
Includes:
Trout Gulch Road (Valencia School Road to ECM).
Includes:
West Beach Road (San Andreas Rd to City Limit) and Lee Road (Hwy 129 to City Limit).
Includes:
Irwin Way, Alameda Ave, Berkeley Way, Larkspur Street, Riverside Road, and Fern Street.